Shell Criterion Port Allen-Spray Dryer & Railcar Loading Foundations

Owner
Shell Criterion
Engineer
RSH Engineering, Inc.
Date of Completion
October 1, 2019
General Contractor
Brown & Root Industrial Services, LLC



No items found.
Project Overview
This project consisted of the construction of a new spray dryer unit and rail car loading foundation that collectively included 980 cubic yards of concrete and 22,000 pounds of reinforcing steel.