Bayou Terrebonne Lock System

Location

Owner

Terrebonne Parish and Consolidated Government

Engineer

GIS Engineering

General Contractor

Sealevel Construction

Status

Project Overview

Sealevel was awarded the general contract for the Bayou Terrebonne Lock System, which included the following scope of work:

  • Construction of an 81’ x 120’ cofferdam with 20’ excavation
  • Installation of (210) 60’ timber piles inside cofferdam
  • Fabrication and installation of (2) 31’ x 15’ miter gates
  • Fabrication of walkways and handrails
  • Construction of a control house