Guerenger Canal Bridge Addition

Location
Arabi, La
Owner
St. Bernard Parish Government
Engineer
Meyer Engineers, Ltd.
General Contractor
Sealevel Construction
Status
Completed in 2024





No items found.
Project Overview
Sealevel constructed the Guerenger Canal Bridge in Arabi, La. The project consisted of:
- Construction of a new road and bridge which included:
- Installation of 3,000 sf of steel sheet piles
- Installation of (24) square concrete piles
- Installation of 300+ cy for approach slabs, bridge abutements, and bridge deck
- 80’ long modular girder bridge