Clifton Ridge Terminal Fire Protection Improvements

Owner

Citgo Petroleum Corporation

Engineer

Arcadis

Date of Completion

April 1, 2020

General Contractor

Benton's Equipment and Construction

Project Overview

Subcontracted by Benton’s Equipment and Construction, Sealevel self-performed the foundation work for a fire protection improvement project. Collectively, the project called for a total of 220 cubic yards of concrete and 17 tons of rebar. The project was completed ahead of schedule, under budget and with zero-lost time incidents.

Other specs of the project included:

  • 110’ x 30’ cofferdam
  • 16′ x 7′ x 18’ drafting pit
  • (2) 12” x 45’ pipe piles
  • flared headwall
  • 50’ x 6’ of retaining wall
  • (4) guard post bollards
  • 2,200 square feet of concrete paving
  • 130 linear feet of curb
  • 20’ x 45’ x 8” boat ramp