Robinson Canal Bridge

Location
Chauvin, La
Owner
LA DOTD
Engineer
LA DOTD
General Contractor
Sealevel Construction
Status
Completed in 2024












No items found.
Project Overview
Serving as the general contractor for the Robinson Canal Bridge project, Sealevel's team completed nearly 98% of the contracted scope, which involved:
- Demolition of the existing bridge
- Installation of 36” square prestressed precast concrete piles up to 128' in length
- Approximately 573 cyds of cast-in-place concrete poured for the (12) bridge decks and (2) approach slabs
- Approximately 168 cyds of cast-in-place concrete for the bridge caps
- Tying of rebar for the concrete barrier rails, bridge decks and approach slabs
- Foundation work for asphalt contractor and the concrete approach slabs
- Placement of 130 tons of rip rap along the banks