Kinder Morgan Platform

Location

Leeville, La

Owner

Kinder Morgan

Engineer

--

General Contractor

Gulf Inland

Status

Completed in 2022

Project Overview

Sealevel Construction worked at three separate Kinder Morgan facilities performing similiar scopes of work. At the largest site, Sealevel:

  • installed 18” x 18” x 90’ square concrete piles and pipe supports
  • installed precast caps and deck
  • installed drilled shafts and concrete pier caps