Nitric Acid Storage Tank

Location
Luling, La
Owner
--
Engineer
--
General Contractor
--
Status
Completed in 2021

No items found.
Project Overview
Sealevel worked with the project owner and engineers to perform (2) 400 KIP compression load tests before installing foundations for a new storage tank foundation. The project’s scope of work included:
- the installation of (148) 7.626″ OD by 105′ long helical piles